CUP: G42F23000440001
MESSA IN SICUREZZA TRATTO DI STRADA IN PIAZZA SANTA ROSALIA§; STRADA DI ACCESSO ALL'I. S. E. RESTIVO§; SISTEMAZIONE DELLA PAVIMEN. MARCIAPIEDI E DELLE AIUOLE ISTITUTO SCOL
SUMMARY OF THE PROJECT
MANUTENZIONE STRAORDINARIA VOLTI ALLA MESSA IN SICUREZZA TRATTO DI STRADA IN PIAZZA SANTA ROSALIA§; STRADA DI ACCESSO ALLISTITUTO SCOLASTICO E. RESTIVO§; SISTEMAZIONE DELLA PAVIMENTAZIONE MARCIAPIEDI E DELLE AIUOLE ISTITUTO SCOLASTICO*VIA PIAZZA SANTA ROSALIA
Implementation indicator
Numero di edifici pubblici o strutture oggetto di intervento
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 21,849.88
of which cohesion funds
€ 21,849.88
Given name | Amount |
---|---|
Development and Cohesion Fund | 21849.88 |
- Economies:
- € 265.12
Payments monitored
€ 21,029.59
of which cohesion funds
€ 21,029.59
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2024 | 21029.59 | 21029.59 | 96 |
State of progress
Completed
Expected start: 18/12/2023
Effective start: 18/12/2023
Expected end: 17/03/2024
Effective end: 19/04/2024
Entities
- Planning body
- COMUNE DI VENTIMIGLIA DI SICILIA
- Beneficiary
- COMUNE DI VENTIMIGLIA DI SICILIA
Programming area
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 21,849.88
- Payments on cohesion funds
- € 21,029.59
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali