CUP: F42F20003620001
Interventi di arredo urbano sul Lungomare Sirimarco
SUMMARY OF THE PROJECT
Arredo urbano sul Lungomare Sirimarco
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 1 km
Download project
Funding monitored
€ 40,187.47
of which cohesion funds
€ 40,187.47
Given name | Amount |
---|---|
Another public source | 40187.47 |
- Economies:
- € 1,396.03
Payments monitored
€ 40,187.47
of which cohesion funds
€ 40,187.47
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 35505.00 | 35505.00 | 88 |
2022 | 4682.47 | 40187.47 | 100 |
State of progress
Completed
Expected start: 11/05/2021
Effective start: 11/05/2021
Expected end: 24/06/2021
Effective end: 23/06/2021
Entities
- Planning body
- COMUNE DI TORTORA
- Beneficiary
- COMUNE DI TORTORA
Programming area
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 40,187.47
- Payments on cohesion funds
- € 40,187.47
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali