CUP: E21B21002790001
ASILO NIDO COMUNALE - COMPLETAMENTO DELLA PAVIMENTAZIONE DEGLI SPAZI ESTERNI, COPERTURA DEL CORNICIONE PERIMETRALE CON LAMIERA IN ACCIAIO GRECATA ED ALTRI LAVORI PER RENDERE FUNZIONALE LA STRUTTURA.
SUMMARY OF THE PROJECT
Completamento spazi esterni e copertura cornicione perimetrale con lamiera grecata
Implementation indicator
Numero di edifici pubblici o strutture oggetto di intervento
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 41,695.19
of which cohesion funds
€ 41,695.19
Given name | Amount |
---|---|
Development and Cohesion Fund | 41695.19 |
- Economies:
- € 1,439.31
Payments monitored
€ 41,695.19
of which cohesion funds
€ 41,695.19
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 41221.17 | 41221.17 | 98 |
2022 | 0 | 41221.17 | 98 |
2023 | 0 | 41221.17 | 98 |
2024 | 474.02 | 41695.19 | 100 |
State of progress
Completed
Expected start: 27/09/2021
Effective start: 27/09/2021
Expected end: 30/11/2021
Effective end: 17/11/2021
Entities
- Planning body
- COMUNE DI SANTA MARIA DI LICODIA
- Beneficiary
- COMUNE DI SANTA MARIA DI LICODIA
Programming area
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 41,695.19
- Payments on cohesion funds
- € 41,695.19
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali