CUP: I72F21000160001
LAVORI DI RIQUALIFICAZIONE DELL'EX MATTATOIO COMUNALE
SUMMARY OF THE PROJECT
LAVORI DI RIQUALIFICAZIONE DELL'EX MATTATOIO COMUNALE
Implementation indicator
Numero di imprese sostenute per introdurre nuovi prodotti che costituiscono una novita' per il mercato
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 105,158.58
of which cohesion funds
€ 105,158.58
Given name | Amount |
---|---|
Another public source | 105158.58 |
Payments monitored
€ 35,052.86
of which cohesion funds
€ 35,052.86
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 35052.86 | 35052.86 | 33 |
State of progress
Open
Expected start: 03/06/2023
Effective start: 03/06/2023
Expected end: 31/12/2023
Effective end: 05/10/2023
Entities
- Planning body
- COMUNE DI SAN PIETRO AVELLANA
- Beneficiary
- COMUNE DI SAN PIETRO AVELLANA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali