CUP: J12F23000680001
REALIZZAZIONE DI PARCHI GIOCHI ALL'INTERNO DELL'AREA A VERDE DI PROPRIETÀ COMUNALE.*LARGO DON LUIGI STURZO*
SUMMARY OF THE PROJECT
REALIZZAZIONE DI PARCHI GIOCHI ALL'INTERNO DELL'AREA A VERDE DI PROPRIETÀ COMUNALE.*LARGO DON LUIGI STURZO*
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 1,720 num
- Achieved
- 1,720 num
Download project
Funding monitored
€ 22,109.18
of which cohesion funds
€ 22,109.18
Given name | Amount |
---|---|
Development and Cohesion Fund | 22109.18 |
- Economies:
- € 223.32
Payments monitored
€ 22,109.06
of which cohesion funds
€ 22,109.06
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2024 | 22109.06 | 22109.06 | 99 |
State of progress
Completed
Expected start: 29/12/2023
Effective start: 29/12/2023
Expected end: 15/02/2024
Effective end: 27/03/2024
Entities
- Planning body
- COMUNE DI RESUTTANO
- Beneficiary
- COMUNE DI RESUTTANO
- Executor
- FORENT GROUP SRLS
Programming area
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 22,109.18
- Payments on cohesion funds
- € 22,109.06
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali