CUP: E21B21003280001
REALIZZAZIONE PARCO DEI NONNI II STRALCIO
SUMMARY OF THE PROJECT
LAVORI DI COMPLETAMENTO DEL PARCO DEI NONNI, REALIZZATO ALL'INTERNO DEL PARCO ROBINSON
Implementation indicator
Spazi aperti creati o ripristinati in aree urbane
- Target
- 1,000 mq
- Achieved
- 1,000 mq
Funding monitored
€ 51,717.45
of which cohesion funds
€ 51,717.45
Given name | Amount |
---|---|
Development and Cohesion Fund | 51717.45 |
- Economies:
- € 3,277.30
Payments monitored
€ 43,425.21
of which cohesion funds
€ 43,425.21
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 43425.21 | 43425.21 | 83 |
State of progress
Open
Expected start: 30/09/2021
Effective start: 30/09/2021
Expected end: 29/11/2021
Effective end: 20/12/2021
Entities
- Planning body
- COMUNE DI RENDE
- Beneficiary
- COMUNE DI RENDE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali