CUP: H99D23000110001
LAVORI PER LA RIQUALIFICAZIONE E MESSA IN SICUREZZA DELLA VIA SANTA MARIA, PER FINALITÀ SOCIALI
SUMMARY OF THE PROJECT
LAVORI PER LA RIQUALIFICAZIONE E MESSA IN SICUREZZA DELLA VIA SANTA MARIA, PER FINALITÀ SOCIALI
Implementation indicator
Popolazione beneficiaria di servizi /infrastrutture migliori (eccetto ICT)
- Target
- 1,325 num
- Achieved
- 1,325 num
Download project
Funding monitored
€ 14,035.68
of which cohesion funds
€ 14,035.68
Given name | Amount |
---|---|
Development and Cohesion Fund | 14035.68 |
- Economies:
- € 3,594.32
Payments monitored
€ 13,753.84
of which cohesion funds
€ 13,753.84
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2024 | 13753.84 | 13753.84 | 97 |
State of progress
Completed
Expected start: 29/06/2023
Effective start: 29/06/2023
Expected end: 30/11/2023
Effective end: 30/11/2023
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA PER MESSA IN SICUREZZA (ESCLUSO DISSESTO IDROGEOLOGICO)
Theme
Territory
Entities
- Planning body
- COMUNE DI NOVARA DI SICILIA
- Beneficiary
- COMUNE DI NOVARA DI SICILIA
Programming area
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 14,035.68
- Payments on cohesion funds
- € 13,753.84
- DCF strategic sector
- Infrastrutture
- DCF area axis