CUP: G98C20000310001
Riqualificazione ed Implementazione dell'Area Giochi presso i Giardini di Largo Runcini
SUMMARY OF THE PROJECT
Riqualificazione ed Implementazione dell'Area Giochi presso i Giardini di Largo Runcini
Implementation indicator
Spazi aperti creati o ripristinati in aree urbane
- Target
- 1,000 mq
- Achieved
- 1,000 mq
Download project
Funding monitored
€ 86,783.00
of which cohesion funds
€ 86,783.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 86783.00 |
Payments monitored
€ 43,391.50
of which cohesion funds
€ 43,391.50
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 43391.50 | 43391.50 | 50 |
State of progress
Open
Expected start: 10/06/2021
Effective start: 26/05/2021
Expected end: 10/07/2021
Effective end: 24/06/2021
Entities
- Planning body
- COMUNE DI MONTORIO AL VOMANO
- Beneficiary
- COMUNE DI MONTORIO AL VOMANO
Programming area
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 86,783.00
- Payments on cohesion funds
- € 43,391.50
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali