CUP: F71B21004920001
LAVORI DI ARREDO URBANO NEL COMUNE DI MIRTO
SUMMARY OF THE PROJECT
SI PREVEDONO INTERVENTI ATTI A MIGLIORARE LA DOTAZIONE DI ARREDI PER COMPLETARE LA VALORIZZAZIONE DEL CENTRO ABITATO CON VALENZA STORICA, SOSTITUZIONE E/O AMPLIAMENTO DELLA SEGNALETICA STRADALE E LA REALIZZAZIONE DI PERCORSI FIRNESS
Implementation indicator
Crescita dell'occupazione nelle imprese che ricevono un sostegno
- Target
- 1 etp
- Achieved
- 1 etp
Funding monitored
€ 27,878.67
of which cohesion funds
€ 27,878.67
Given name | Amount |
---|---|
Development and Cohesion Fund | 27878.67 |
- Economies:
- € 1,261.33
Payments monitored
€ 27,362.30
of which cohesion funds
€ 27,362.30
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 14570.00 | 14570.00 | 52 |
2023 | 12792.30 | 27362.30 | 98 |
State of progress
Completed
Expected start: 30/09/2021
Effective start: 30/09/2021
Expected end: 04/11/2021
Effective end: 31/05/2022
Entities
- Planning body
- COMUNE DI MIRTO
- Beneficiary
- COMUNE DI MIRTO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali
Other projects in territory
Same theme
Same type of investment
BANDA ULTRALARGA NELLE AREE BIANCHE DEL TERRITORIO DELLA REGIONE SICILIA CON FONDI PON | € 17,100,000 |