CUP: G82F22000500005
¿LAVORI DI MANUTENZIONE STRAORDINARIA E COMPLETAMENTO DELL¿ARREDO URBANO E DEL VERDE PUBBLICO DI PIAZZETTA MORA
SUMMARY OF THE PROJECT
¿LAVORI DI MANUTENZIONE STRAORDINARIA E COMPLETAMENTO DELL¿ARREDO URBANO E DEL VERDE PUBBLICO DI PIAZZETTA MORA
Implementation indicator
Spesa pubblica ammessa totale
- Target
- 42,516.50 euro
- Achieved
- 41,376.73 euro
Download project
Funding monitored
€ 41,376.73
of which cohesion funds
€ 41,376.73
Given name | Amount |
---|---|
Development and Cohesion Fund | 41376.73 |
- Economies:
- € 1,139.77
Payments monitored
€ 20,688.37
of which cohesion funds
€ 20,688.37
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 20688.37 | 20688.37 | 50 |
State of progress
Open
Expected start: 22/12/2022
Effective start: 22/12/2022
Expected end: 20/06/2023
Effective end: 19/05/2023
Entities
- Planning body
- COMUNE DI MELISSANO
- Beneficiary
- COMUNE DI MELISSANO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali