CUP: D37H21000540001
INTERVENTI DI RIQUALIFICAZIONE IMMOBILI COMUNALI (EDIFICIO SCOLASTICO SCUOLA PRIMARIA DI VIA MADONNELLA E CIMITERO COMUNALE)
SUMMARY OF THE PROJECT
RIQUALIFICAZIONE EDIFICIO SCOLASTICO
Implementation indicator
Numero edifici scolastici oggetto dell'intervento
- Target
- 1 num
- Achieved
- -
Download project
Funding monitored
€ 32,827.50
of which cohesion funds
€ 32,827.50
Given name | Amount |
---|---|
Development and Cohesion Fund | 32827.50 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 07/06/2021
Effective start: 07/06/2021
Expected end: 29/12/2021
Effective end: not available
Entities
- Planning body
- COMUNE DI MARANO PRINCIPATO
- Implementing body
- COMUNE DI MARANO MARCHESATO
- Beneficiary
- COMUNE DI MARANO PRINCIPATO
- Executor
- TRE M COSTRUZIONI SRL
Programming area
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 32,827.50
- Payments on cohesion funds
- € 0.00
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali
Other projects in territory
Same theme
RIQUALIFICAZIONE CIMITERO COMUNALE (COMPLETAMENTO) | € 32,552 |
¿INTERVENTI DI RIQUALIFICAZIONE URBANA E SOCIALE DI AREE COMUNALI¿ (ANNUALITA¿ 2022). | € 31,901 |