CUP: D91B21003480005
TERZO INTERVENTO DI COMPLETAMENTO DEL CIMITERO COMUNALE
SUMMARY OF THE PROJECT
Intervento di completamento dei nuovi loculi e pavimentazioni del cimitero comunale
Implementation indicator
Popolazione beneficiaria di servizi /infrastrutture migliori (eccetto ICT)
- Target
- 600 num
- Achieved
- 600 num
Download project
Funding monitored
€ 10,775.11
of which cohesion funds
€ 9,590.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 9590.00 |
Municipality | 1185.11 |
- Economies:
- € 216.15
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 28/09/2021
Effective start: 28/09/2021
Expected end: 27/11/2021
Effective end: 27/11/2021
Entities
- Planning body
- COMUNE DI DUALCHI
- Beneficiary
- COMUNE DI DUALCHI
Programming area
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 9,590.00
- Payments on cohesion funds
- € 0.00
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali
Other projects in territory
Same theme
SECONDO INTERVENTO DI COMPLETAMENTO DEL CIMITERO COMUNALE | € 10,148 |
Same type of investment
Ecocentro Dualchi | € 66,388 |
Reti per la sicurezza del cittadino e del territorio - RdS Fase 2 - Comune di Dualchi | € 34,762 |
SECONDO INTERVENTO DI COMPLETAMENTO DEL CIMITERO COMUNALE | € 10,148 |