CUP: C37H21000570001
LAVORI DI: ¿MANUTENZIONE STRAORDINARIA CON EFFICIENTAMENTO ENERGETICO SCUOLA PRIMARIA. PRIMO PIANO¿.
SUMMARY OF THE PROJECT
MANUTENZIONE STRAORDINARIA CON EFFICIENTAMENTO ENERGETICO SCUOLA PRIMARIA. PRIMO PIANO.
Implementation indicator
Interventi per la messa in sicurezza degli edifici scolastici
- Target
- 10 num
- Achieved
- 10 num
Download project
Funding monitored
€ 28,626.38
of which cohesion funds
€ 28,626.38
Given name | Amount |
---|---|
Development and Cohesion Fund | 28626.38 |
- Economies:
- € 403.62
Payments monitored
€ 28,626.37
of which cohesion funds
€ 28,626.37
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 28626.37 | 28626.37 | 99 |
State of progress
Completed
Expected start: 12/07/2021
Effective start: 12/07/2021
Expected end: 05/12/2021
Effective end: 19/11/2021
Entities
- Planning body
- COMUNE DI CRECCHIO
- Implementing body
- COMUNE DI CRECCHIO
- Beneficiary
- COMUNE DI CRECCHIO
- Executor
- EDILSTELLA DI LUCIANI & DI PASQUANTONIO S.R.L., VIA ENRICO TOTI, 67, 63077 MONSAMPOLO DEL TRONTO (AP)
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali