CUP: D67H21003100001
LAVORI ALL'INTERNO DEL CIMITERO COMUNALE
SUMMARY OF THE PROJECT
LAVORI ALL'INTERNO DEL CIMITERO COMUNALE
Implementation indicator
Spesa pubblica ammessa totale
- Target
- 40,836.50 euro
- Achieved
- 39,706.81 euro
Download project
Funding monitored
€ 39,706.81
of which cohesion funds
€ 39,706.81
Given name | Amount |
---|---|
Development and Cohesion Fund | 39706.81 |
- Economies:
- € 1,129.69
Payments monitored
€ 39,706.81
of which cohesion funds
€ 39,706.81
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 39706.81 | 39706.81 | 100 |
State of progress
Completed
Expected start: 02/07/2021
Effective start: 02/07/2021
Expected end: 15/09/2021
Effective end: 09/08/2021
Entities
- Planning body
- COMUNE DI CORSANO
- Beneficiary
- COMUNE DI CORSANO
Programming area
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 39,706.81
- Payments on cohesion funds
- € 39,706.81
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali