CUP: F62F22000550001
Rifacimento e adeguamento della viabilità locale nelle Frazioni Arcuri e Gigliotti
SUMMARY OF THE PROJECT
Rifacimento e adeguamento della viabilità locale nelle Frazioni Arcuri e Gigliotti
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate di cui: TEN-T
- Target
- 0.15 km
- Achieved
- 0.15 km
Download project
Funding monitored
€ 16,332.80
of which cohesion funds
€ 16,332.80
Given name | Amount |
---|---|
Development and Cohesion Fund | 16332.80 |
- Economies:
- € 862.20
Payments monitored
€ 15,945.60
of which cohesion funds
€ 15,945.60
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2024 | 15945.60 | 15945.60 | 97 |
State of progress
Completed
Expected start: 01/09/2022
Effective start: 29/07/2022
Expected end: 31/12/2022
Effective end: 29/07/2022
Entities
- Planning body
- COMUNE DI COLOSIMI
- Implementing body
- COMUNE DI COLOSIMI
- Beneficiary
- COMUNE DI COLOSIMI
Programming area
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 16,332.80
- Payments on cohesion funds
- € 15,945.60
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali