CUP: E52F22000390001
ILLUMINAZIONE DELLE MURA INTERNE ED ESTERNE DEL CASTELLO DI SAVUTO E RIQUALIFICAZIONE DELL'AREA ANTISTANTE LA FONTANA DI CECE
SUMMARY OF THE PROJECT
ILLUMINAZIONE DELLE MURA INTERNE ED ESTERNE DEL CASTELLO DI SAVUTO E RIQUALIFICAZIONE DELL'AREA ANTISTANTE LA FONTANA DI CECE
Implementation indicator
Spazi aperti creati o ripristinati in aree urbane
- Target
- 250 mq
- Achieved
- 250 mq
Funding monitored
€ 17,382.40
of which cohesion funds
€ 17,382.40
Given name | Amount |
---|---|
Development and Cohesion Fund | 17382.40 |
- Economies:
- € 0.10
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Not started
Expected start: 22/06/2022
Effective start: 22/06/2022
Expected end: 28/09/2022
Effective end: 28/09/2022
Entities
- Planning body
- COMUNE DI CLETO
- Implementing body
- COMUNE DI CLETO
- Beneficiary
- COMUNE DI CLETO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali