CUP: H52F22000410001
FONDO INFRASTRUTTURE SOCIALI VARI INTERVENTI
SUMMARY OF THE PROJECT
RIPRISTINO FOSSO DI SCOLO ESISTENTE RELATIVO ALLA RACCOLTA, REGIMENTAZIONE E SMALTIMENTO DELLE ACQUE PIOVANE, PROVENIENTE DALLA ALTA DELL'ABITATO DELLA FRAZIONE MARCELLINA, IN LOCALITÃ FIORENTINA"
Implementation indicator
Ampliamento lunghezza rete
- Target
- 222 m
- Achieved
- 180 m
Funding monitored
€ 40,262.60
of which cohesion funds
€ 40,262.60
Given name | Amount |
---|---|
Development and Cohesion Fund | 40262.60 |
- Economies:
- € 193.90
Payments monitored
€ 40,262.60
of which cohesion funds
€ 40,262.60
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 40262.60 | 40262.60 | 100 |
State of progress
Completed
Expected start: 30/09/2022
Effective start: 30/09/2022
Expected end: 29/12/2022
Effective end: 28/10/2023
Entities
- Planning body
- COMUNE DI SANTA MARIA DEL CEDRO
- Beneficiary
- COMUNE DI SANTA MARIA DEL CEDRO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali