CUP: F79H23000020001
EDIFICIO SCOLASTICO - SCUOLA DELL'INFANZIA - VIA PROVINCIALE - RISTRUTTURAZIONE
SUMMARY OF THE PROJECT
DEMOLIZIONE DI ALCUNE PARETI E SANITARI, SOSTITUZIONE DI INFISSI, SPOSTAMENTO E INSERIMENTO DI NUOV PORTE
Implementation indicator
Numero edifici scolastici oggetto dell'intervento
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 8,448.00
of which cohesion funds
€ 8,448.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 8448.00 |
- Economies:
- € 2.00
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 30/08/2023
Effective start: 30/08/2023
Expected end: 13/09/2023
Effective end: 12/09/2023
Entities
- Planning body
- COMUNE DI CENADI
- Beneficiary
- COMUNE DI CENADI
Programming area
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 8,448.00
- Payments on cohesion funds
- € 0.00
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali