CUP: F72F22000970001
INTERVENTO PER LA RIQUALIFICAZIONE FUNZIONALE DEL MURO DI CINTA DEL CIMITERO COMUNALE
SUMMARY OF THE PROJECT
INTERVENTO PER LA RIQUALIFICAZIONE FUNZIONALE DEL MURO DI CINTA DEL CIMITERO COMUNALE
Implementation indicator
Superficie opere e/o impianti realizzati
- Target
- 265 mq
- Achieved
- 265 mq
Download project
Funding monitored
€ 35,019.28
of which cohesion funds
€ 35,019.28
Given name | Amount |
---|---|
Development and Cohesion Fund | 35019.28 |
- Economies:
- € 708.22
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Not started
Expected start: 29/12/2022
Effective start: 29/12/2022
Expected end: 29/03/2023
Effective end: 29/03/2023
Entities
- Planning body
- COMUNE DI ARNESANO
- Implementing body
- COMUNE DI ARNESANO
- Beneficiary
- COMUNE DI ARNESANO
- Executor
- COMUNE DI ARNESANO
Programming area
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 35,019.28
- Payments on cohesion funds
- € 0.00
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali