CUP: H95E22000180001
REALIZZAZIONE E ALLESTIMENTO DELLA CUCINA A SERVIZIO DELLA MENSA DELLA NUOVA SCUOLA IN VIA CASILI
SUMMARY OF THE PROJECT
REALIZZAZIONE E ALLESTIMENTO DELLA CUCINA A SERVIZIO DELLA MENSA DELLA NUOVA SCUOLA IN VIA CASILI
Implementation indicator
Capacità dell'infrastruttura per l'assistenza all'infanzia o l'istruzione sostenuta
- Target
- 50 num
- Achieved
- 50 num
Funding monitored
€ 13,249.20
of which cohesion funds
€ 13,249.20
Given name | Amount |
---|---|
Development and Cohesion Fund | 13249.20 |
- Economies:
- € 0.80
Payments monitored
€ 13,249.20
of which cohesion funds
€ 13,249.20
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 13249.20 | 13249.20 | 100 |
State of progress
Completed
Expected start: 19/05/2022
Effective start: 19/05/2022
Expected end: 30/09/2022
Effective end: 07/07/2022
Entities
- Planning body
- COMUNE DI ALFEDENA
- Beneficiary
- COMUNE DI ALFEDENA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali