CUP: G21B21002550005
LAVORI DI ADEGUAMENTO SISMICO DELLA SCUOLA PRIMARIA PASTRENGO COMPLETAMENTO
SUMMARY OF THE PROJECT
LAVORI DI ADEGUAMENTO SISMICO DELLA SCUOLA PRIMARIA PASTRENGO COMPLETAMENTO
Implementation indicator
Numero di partecipanti alla formazione
- Target
- 150 num
- Achieved
- 150 num
Funding monitored
€ 224,488.10
of which cohesion funds
€ 98,513.75
Given name | Amount |
---|---|
Development and Cohesion Fund | 98513.75 |
Municipality | 125974.35 |
- Economies:
- € 0.01
Payments monitored
€ 49,212.13
of which cohesion funds
€ 49,212.13
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 49212.13 | 49212.13 | 21 |
State of progress
Open
Expected start: 24/09/2021
Effective start: 24/09/2021
Expected end: 20/06/2022
Effective end: 15/05/2022
Entities
- Planning body
- COMUNE DI ACRI
- Beneficiary
- COMUNE DI ACRI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali