CUP: J97G20000070001
INTERVENTI DIFFUSI DI MIGLIORAMENTO DELL'INFRASTRUTTURA FERROVIARIA IN CAMPANIA - ANNUALITÃ 2021
SUMMARY OF THE PROJECT
INTERVENTI DIFFUSI DI UPGRADING ALL'INFRASTRUTTURA FERROVIARIA DELLA REGIONE CAMPANIA, SULLE LINEE FRATTAMAGGIORE - NAPOLI C.LE, PORTICI - SALERNO, AVERSA - CASERTA , FORMIA - FRATTAMAGGIORE E IL NODO DI MARCIANISE/MADDALONI. GLI INTERVENTI DI ARMAMENTO CONSISTONO NEL RINNOVO DI BINARI E DEVIATOI.
Implementation indicator
Lunghezza totale delle linee ferroviarie ricostruite o rinnovate
- Target
- 90 km
- Achieved
- 90 km
Download project
Funding monitored
€ 0.00
of which cohesion funds
€ 16,421,330.60
Given name | Amount |
---|
Payments monitored
€ 15,389,315.55
of which cohesion funds
€ 11,325,198.17
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 6671867.39 | 6671867.39 | 0 |
2022 | 5082336.52 | 11754203.91 | 0 |
2023 | 3635111.64 | 15389315.55 | 0 |
State of progress
Undetermined
Expected start: 01/09/2018
Effective start: not available
Expected end: 30/04/2023
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- RETE FERROVIARIA ITALIANA SPA
Programming area
- Programme
- NOP ERDF INFRASTRUCTURES AND NETWORKS
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 16,421,330.60
- Payments on cohesion funds
- € 11,325,198.17
- Axis
- Potenziamento della mobilità regionale per una ripresa verd
- Specific objective
- Miglioramento della domanda potenziale significativa, anche mobilità regionale, attraverso integrazione modale e miglioramento dei collegamenti multimodali