CUP: J97J19000070001
INTERVENTI DIFFUSI DI MIGLIORAMENTO DELL'INFRASTRUTTURA FERROVIARIA IN CAMPANIA - ANNUALITÃ 2019
SUMMARY OF THE PROJECT
INTERVENTI DIFFUSI DI UPGRADING ALL'INFRASTRUTTURA FERROVIARIA DELLA REGIONE CAMPANIA, SULLE LINEE FRATTAMAGGIORE - NAPOLI C.LE, PORTICI - SALERNO, AVERSA - CASERTA , FORMIA - FRATTAMAGGIORE E IL NODO DI MARCIANISE/MADDALONI. GLI INTERVENTI DI ARMAMENTO CONSISTONO NEL RINNOVO DI BINARI E DEVIATOI.
Implementation indicator
Lunghezza totale delle linee ferroviarie ricostruite o rinnovate
- Target
- 90 km
- Achieved
- 90 km
Download project
Funding monitored
€ 0.00
of which cohesion funds
€ 3,946,180.93
Given name | Amount |
---|
Payments monitored
€ 3,946,180.93
of which cohesion funds
€ 3,946,180.93
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 3015210.76 | 3015210.76 | 0 |
2021 | 0 | 3015210.76 | 0 |
2022 | 0 | 3015210.76 | 0 |
2023 | 930970.17 | 3946180.93 | 0 |
State of progress
Undetermined
Expected start: 06/08/2019
Effective start: 06/08/2019
Expected end: 02/11/2022
Effective end: 02/11/2022
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- RETE FERROVIARIA ITALIANA SPA
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- NOP ERDF INFRASTRUCTURES AND NETWORKS
- Axis
- Potenziamento della mobilità regionale per una ripresa verd
- Specific objective
- Miglioramento della domanda potenziale significativa, anche mobilità regionale, attraverso integrazione modale e miglioramento dei collegamenti multimodali