CUP: J44H14000080006
LAVORI DI MANUTENZIONE STRAORD. DELL'EDIFICIO DELLA SCUOLA DELL'INFANZIA LAVORI DI MESSA IN SICUREZZA, RISTRUT. EFFICENTAMENTO ENERGETICO ED ADEG. IMPIANTISTICO DELLA SC. DELL'INFANZIA.
SUMMARY OF THE PROJECT
LAVORI DI MANUTENZIONE STRAORD. DELL'EDIFICIO DELLA SCUOLA DELL'INFANZIA LAVORI DI MESSA IN SICUREZZA, RISTRUT. EFFICENTAMENTO ENERGETICO ED ADEG. IMPIANTISTICO DELLA SC. DELL'INFANZIA.
Implementation indicator
Imprese beneficiate
- Target
- 3 num
- Achieved
- 3 num
Funding monitored
€ 211,103.83
of which cohesion funds
€ 185,271.94
Given name | Amount |
---|---|
Development and Cohesion Fund | 185271.94 |
Municipality | 25831.89 |
- Economies:
- € 14,728.06
Payments monitored
€ 202,708.84
of which cohesion funds
€ 179,521.90
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 11419.20 | 11419.20 | 5 |
2015 | 150547.50 | 161966.70 | 76 |
2016 | 40742.14 | 202708.84 | 96 |
State of progress
Completed
Expected start: 16/06/2015
Effective start: 16/06/2015
Expected end: 13/12/2015
Effective end: 31/12/2015
Entities
- Planning body
- MIUR ISTRUZIONE
- Implementing body
- COMUNE DI PUTIFIGARI
- Beneficiary
- COMUNE DI PUTIFIGARI
- Executor
- COMUNE DI PUTIFIGARI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELL'ISTRUZIONE E DEL MERITO
- Policy Area
- Istruzione e Formazione
- Sector of intervention
- Strutture educative e formative