CUP: E86J14000450001
COMPLETAMENTO MESSA A NORMA, ADEGUAMENTO ENERGETICO E MANUTENZIONE EDIFICIO SCOLASTICO SOVRACOMUNALE DELL'ISTITUTO COMPRENSIVO GIOVANNI XXIII
SUMMARY OF THE PROJECT
COMPLETAMENTO MESSA A NORMA, ADEGUAMENTO ENERGETICO E MANUTENZIONE EDIFICIO SCOLASTICO SOVRACOMUNALE DELL'ISTITUTO COMPRENSIVO GIOVANNI XXIII
Implementation indicator
Imprese beneficiate
- Target
- 5 num
- Achieved
- 5 num
Download project
Funding monitored
€ 423,451.30
of which cohesion funds
€ 423,451.30
Given name | Amount |
---|---|
Development and Cohesion Fund | 423451.30 |
- Economies:
- € 76,548.70
Payments monitored
€ 422,091.59
of which cohesion funds
€ 422,091.59
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 400475.95 | 400475.95 | 94 |
2017 | 21615.64 | 422091.59 | 99 |
State of progress
Completed
Expected start: 10/03/2015
Effective start: 10/03/2015
Expected end: 31/12/2015
Effective end: 31/08/2016
Entities
- Planning body
- MIUR ISTRUZIONE
- Implementing body
- COMUNE DI SALICETO
- Beneficiary
- COMUNE DI SALICETO
- Executor
- COMUNE DI SALICETO
Programming area
- Programme
- PSC MINISTERO DELL'ISTRUZIONE E DEL MERITO
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 423,451.30
- Payments on cohesion funds
- € 422,091.59
- Policy Area
- Istruzione e Formazione
- Sector of intervention
- Strutture educative e formative