CUP: B84H13000250004
SCUOLA PRIMARIA 'M.COPPINO'. OPERE DI MESSA IN SICUREZZA CONTROSOFFITTI.
SUMMARY OF THE PROJECT
SCUOLA PRIMARIA 'M.COPPINO'. OPERE DI MESSA IN SICUREZZA CONTROSOFFITTI.
Implementation indicator
Imprese beneficiate
- Target
- 2 num
- Achieved
- 2 num
Download project
Funding monitored
€ 28,652.06
of which cohesion funds
€ 28,652.06
Given name | Amount |
---|---|
Development and Cohesion Fund | 28652.06 |
- Economies:
- € 2,347.94
Payments monitored
€ 27,663.42
of which cohesion funds
€ 27,663.42
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2013 | 27663.42 | 27663.42 | 96 |
State of progress
Completed
Expected start: 18/11/2013
Effective start: 18/11/2013
Expected end: 17/12/2013
Effective end: 15/01/2014
Entities
- Planning body
- MIUR ISTRUZIONE
- Implementing body
- COMUNE DI ALBA
- Beneficiary
- COMUNE DI ALBA
- Executor
- COMUNE DI ALBA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELL'ISTRUZIONE E DEL MERITO
- Policy Area
- Istruzione e Formazione
- Sector of intervention
- Strutture educative e formative