CUP: J51E14000290005
Lavori di recupero ed ampliamento della Scuola Primaria di Molinetto 'C. Abba' 1 fase
SUMMARY OF THE PROJECT
Lavori di recupero ed ampliamento della Scuola Primaria di Molinetto 'C. Abba' 1 fase
Implementation indicator
Imprese beneficiate
- Target
- 2 num
- Achieved
- 2 num
Download project
Funding monitored
€ 1,213,378.60
of which cohesion funds
€ 939,445.48
Given name | Amount |
---|---|
Development and Cohesion Fund | 939445.48 |
Municipality | 273933.12 |
- Economies:
- € 446,792.92
Payments monitored
€ 1,043,111.41
of which cohesion funds
€ 939,445.48
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 212053.47 | 212053.47 | 17 |
2016 | 831057.94 | 1043111.41 | 85 |
State of progress
Open
Expected start: 20/07/2015
Effective start: 20/07/2015
Expected end: 16/01/2016
Effective end: 16/01/2016
Entities
- Planning body
- MINISTERO DELL'ISTRUZIONE E DEL MERITO
- Implementing body
- COMUNE DI MAZZANO
- Beneficiary
- COMUNE DI MAZZANO
- Executor
- COMUNE DI MAZZANO
Programming area
- Programme
- PSC MINISTERO DELL'ISTRUZIONE E DEL MERITO
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 939,445.48
- Payments on cohesion funds
- € 939,445.48
- Policy Area
- Istruzione e Formazione
- Sector of intervention
- Strutture educative e formative