CUP: B24H14001460005
LAVORI DI MESSA IN SICUREZZA DELLA SCUOLA MEDIA E DELLA COPERTURA DEL PLESSO SCOLASTICO DI VIA DEL FAGGETO
SUMMARY OF THE PROJECT
LAVORI DI MESSA IN SICUREZZA DELLA SCUOLA MEDIA E DELLA COPERTURA DEL PLESSO SCOLASTICO DI VIA DEL FAGGETO
Implementation indicator
Imprese beneficiate
- Target
- 7 num
- Achieved
- 7 num
Download project
Funding monitored
€ 175,611.26
of which cohesion funds
€ 161,318.47
Given name | Amount |
---|---|
Development and Cohesion Fund | 161318.47 |
Municipality | 14292.79 |
- Economies:
- € 63,371.46
Payments monitored
€ 171,277.04
of which cohesion funds
€ 157,303.78
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 113734.22 | 113734.22 | 64 |
2016 | 57542.82 | 171277.04 | 97 |
State of progress
Completed
Expected start: 23/02/2015
Effective start: 23/02/2015
Expected end: 15/07/2015
Effective end: 13/04/2016
Entities
- Planning body
- MINISTERO DELL'ISTRUZIONE E DEL MERITO
- Implementing body
- COMUNE DI ALLUMIERE
- Beneficiary
- COMUNE DI ALLUMIERE
- Executor
- COMUNE DI ALLUMIERE
Programming area
- Programme
- PSC MINISTERO DELL'ISTRUZIONE E DEL MERITO
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 161,318.47
- Payments on cohesion funds
- € 157,303.78
- Policy Area
- Istruzione e Formazione
- Sector of intervention
- Strutture educative e formative
Other projects in territory
Same theme
INTERVENTI DI ADEGUAMENTO E ADATTAMENTO FUNZIONALE DEGLI SPAZI E DELLE AULE DIDATTICHE IN CONSEGUENZA DELLEMERGENZA SANITARIA DA COVID 9 | € 15,000 |
ACQUISIZIONE COMPETENZE FLASH | € 9,750 |
Same type of investment
Sistemazione idrogeologica Le Terre. | € 2,142,287 |
COMUNE DI ALLUMIERE - Intervento sulla strada comunale "Via Bandita del Buoi" | € 163,522 |