CUP: H56J16000170007
COPERTURA DI RETE LANWLAN
SUMMARY OF THE PROJECT
QUESTO PROGETTO METTER A DISPOSIZIONE DEI DOCENTI E DEGLI ALUNNI UN INFRASTRUTTURA DI RETE WIFI CONTROLLATA E CENTRALMENTE GESTITA CHE PERMETTER LA DISTRIBUZIONE IN RETE DELLE RISORSE INFORMATICHE DELLISTITUTO TRA CUI LACCESSO AD INTERNET. LA SOLUZIONE PREVEDE LA REALIZZAZIONE DI UNA INFRASTRUTTURA WIFI DI NUOVA GENERAZIONE DISTRIBUITA E CENTRALMENTE GESTITA DA UN CONTROLLER DELLE RETE WIFI. LA SICUREZZA DEGLI ACCESSI VIENE FILTRATA E CONTROLLATA DA UN FIREWALL PER EVITARE UN USO IMPROPRIO DELLA RETE INTERNET. LA STRUTTURA HARDWARE SAR COSTITUITA DA UN CABLAGGIO STRUTTURATO PER ALIMENTARE E COLLEGARE GLI ACCESS POINT.
Funding monitored
€ 18,496.30
of which cohesion funds
€ 18,496.30
Given name | Amount |
---|---|
European Union | 9248.15 |
Revolving Fund | 9248.15 |
Payments monitored
€ 17,875.49
of which cohesion funds
€ 17,875.49
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 118.00 | 118.00 | 0 |
2017 | 17757.49 | 17875.49 | 96 |
State of progress
Completed
Expected start: 06/06/2016
Effective start: 30/08/2016
Expected end: 30/10/2016
Effective end: 13/02/2017
Entities
- Planning body
- MIUR ISTRUZIONE
- Beneficiary
- DI CASALE SCODOSIA SCULDASCIA
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- NOP ERDF ESF EDUCATION
- Axis
- INFRASTRUTTURE PER L'ISTRUZIONE
- Specific objective
- Diffusione della società della conoscenza nel mondo della scuola e della formazione e adozione di approcci didattici innovativi