Updated on 31/08/2024
Funding monitored € 25,410.00 of which cohesion funds € 25,410.00
Given name Amount
Revolving Fund25410.00
Payments monitored € 22,221.07 of which cohesion funds € 22,221.07
Year Amount Cumulative amount Percentage on public financing
202222221.0722221.0787

State of progress

Open
Expected start: 31/05/2021
Effective start: 05/04/2022
Expected end: 31/07/2022
Effective end: 05/07/2022

Entities

Planning body
MIUR ISTRUZIONE
Beneficiary
I I.C. VERGA CANICATTINI BAGNI

Programming area

Programme
POC PER LA SCUOLA COMPETENZE E AMBIENTI PER L'APPRENDIMENTO
2014-2020 Cohesion Action Plan
2014-2020 Cohesion Action Plan
Cohesion funds
€ 25,410.00
Payments on cohesion funds
€ 22,221.07
CAP area axis
Istruzione
CAP action line
Miglioramento delle competenze chiave degli alievi

Other projects in territory