CUP: B97D18000330003
23.07.I.80.9.0 Rete telematica provinciale: Posa fibra ottica S. Leonardo in P. - Vipiteno
SUMMARY OF THE PROJECT
Posa fibra ottica S. Leonardo in Passiria - Vipiteno
Implementation indicator
Estensione della rete
- Target
- 32 km
- Achieved
- 32 km
Download project
Funding monitored
€ 115,152.05
of which cohesion funds
€ 115,152.05
Given name | Amount |
---|---|
Development and Cohesion Fund | 115152.05 |
Payments monitored
€ 115,152.05
of which cohesion funds
€ 115,152.05
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 17453.92 | 17453.92 | 15 |
2016 | 0 | 17453.92 | 15 |
2017 | 0 | 17453.92 | 15 |
2018 | 0 | 17453.92 | 15 |
2019 | 97698.13 | 115152.05 | 100 |
State of progress
Completed
Expected start: 10/10/2018
Effective start: 10/10/2018
Expected end: 21/06/2019
Effective end: 21/06/2019
Entities
- Planning body
- MIMIT - MINISTERO DELLE IMPRESE E DEL MADE IN ITALY
- Implementing body
- PROVINCIA AUTONOMA DI BOLZANO
- Beneficiary
- PROVINCIA AUTONOMA DI BOLZANO
- Executor
-
Sime Telecomunicazioni Spa
M.S.A. di Tonini dr ing Andrea
Programming area
- Programme
- PSC MINISTRY OF ENTERPRISES AND MADE IN ITALY
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 115,152.05
- Payments on cohesion funds
- € 115,152.05
- Policy Area
- Digitalizzazione
- Sector of intervention
- Connettivita' digitale
Other projects in territory
Same theme
Rete telematica provincialeCollegamento Merano - S.Leonardo in Passiria | € 875,668 |
23.07.I.80.5.0 Rete telematica provinciale: Collegamento San Leonardo in Passiria - Passo Giovo | € 345,734 |