23.07.I.65.2.0 Rete telematica provinciale: Posa fibra ottica Ponte Gardena - Laion
SUMMARY OF THE PROJECT
Sottotubazione tubi con microtubi, soffiaggio microcavi a fibre ottiche, giunzione fibre ottiche, terminazione cavi in ODF o MOC, terminazione cavi in ODF o MOC tra Ponte Gardena e Laion
Implementation indicator
Estensione della rete
- Target
- 5.20 km
- Achieved
- 5.20 km
Download project
Funding monitored
€ 78,059.53
of which cohesion funds
€ 78,059.53
Given name | Amount |
---|---|
Development and Cohesion Fund | 78059.53 |
Payments monitored
€ 78,059.53
of which cohesion funds
€ 78,059.53
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 78059.53 | 78059.53 | 100 |
State of progress
Completed
Expected start: 13/09/2018
Effective start: 13/09/2018
Expected end: 04/03/2019
Effective end: 04/03/2019
Entities
- Planning body
- MIMIT - MINISTERO DELLE IMPRESE E DEL MADE IN ITALY
- Implementing body
- PROVINCIA AUTONOMA DI BOLZANO
- Beneficiary
- PROVINCIA AUTONOMA DI BOLZANO
- Executor
-
MET Srl
M.S.A. di Tonini dr ing Andrea
Programming area
- Programme
- PSC MINISTRY OF ENTERPRISES AND MADE IN ITALY
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 78,059.53
- Payments on cohesion funds
- € 78,059.53
- Policy Area
- Digitalizzazione
- Sector of intervention
- Connettivita' digitale