CUP: B14I19000920003
23.07.I.13.20.0 Rete telematica provinciale. Collegamento in fibra ottica delle gallerie della Val Pusteria
SUMMARY OF THE PROJECT
Posa di un cavo in fibra ottica nelle tubazioni vuote nelle gallerie della Val Pusteria
Implementation indicator
Estensione della rete
- Target
- 2.80 km
- Achieved
- 1 km
Download project
Funding monitored
€ 108,396.36
of which cohesion funds
€ 108,396.36
Given name | Amount |
---|---|
Development and Cohesion Fund | 108396.36 |
Payments monitored
€ 108,396.36
of which cohesion funds
€ 108,396.36
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 108396.36 | 108396.36 | 100 |
State of progress
Completed
Expected start: 16/03/2020
Effective start: 16/03/2020
Expected end: 19/06/2020
Effective end: 19/06/2020
Entities
- Planning body
- MIMIT - MINISTERO DELLE IMPRESE E DEL MADE IN ITALY
- Implementing body
- PROVINCIA AUTONOMA DI BOLZANO
- Beneficiary
- PROVINCIA AUTONOMA DI BOLZANO
- Executor
-
Dr. Ing. Stefano Brunetti
BRUNNER MATTHIAS & LEITER PAUL OHG
Programming area
- Programme
- PSC MINISTRY OF ENTERPRISES AND MADE IN ITALY
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 108,396.36
- Payments on cohesion funds
- € 108,396.36
- Policy Area
- Digitalizzazione
- Sector of intervention
- Connettivita' digitale