CUP: I12C22001130006
EFFICIENTAMENTO ENERGETICO DI VIA MARCO POLO
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO DI VIA MARCO POLO
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 372,755.87 KWh/a
- Achieved
- 372,755.87 KWh/a
Funding monitored
€ 215,218.08
of which cohesion funds
€ 215,218.08
Given name | Amount |
---|---|
European Union | 215218.08 |
Payments monitored
€ 215,218.08
of which cohesion funds
€ 215,218.08
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 215218.08 | 215218.08 | 100 |
State of progress
Completed
Expected start: 01/03/2023
Effective start: 17/04/2023
Expected end: 30/06/2023
Effective end: 31/08/2023
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI FERNO
- Beneficiary
- COMUNE DI FERNO
- Executor
- COMUNE DI FERNO
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili