CUP: H14J22000760001
Efficientamento energetico di PIAZZA DI SANTA MARIA
SUMMARY OF THE PROJECT
Efficientamento energetico di PIAZZA DI SANTA MARIA
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 7,193.90 KWh/a
- Achieved
- 7,193.90 KWh/a
Download project
Funding monitored
€ 129,596.53
of which cohesion funds
€ 129,596.53
Given name | Amount |
---|---|
European Union | 129596.53 |
Payments monitored
€ 129,596.53
of which cohesion funds
€ 129,596.53
100%
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 129596.53 | 129596.53 | 100 |
State of progress
Completed
Expected start: 12/02/2023
Effective start: 26/06/2023
Expected end: 30/06/2023
Effective end: 28/07/2023
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI PELLIZZANO
- Beneficiary
- COMUNE DI PELLIZZANO
- Executor
- COMUNE DI PELLIZZANO
Programming area
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 129,596.53
- Payments on cohesion funds
- € 129,596.53
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili
Other projects in territory
Same theme
Same type of investment
Mobilita Sostenibile: installazione di punti di ricarica per automezzi ibridi ed elettrici e per e-bike | € 300,000 |