CUP: E44D22003840001
Efficientamento energetico di Via Aldo Moro
SUMMARY OF THE PROJECT
Efficientamento energetico di Via Aldo Moro
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 31,438.53 KWh/a
- Achieved
- 31,438.53 KWh/a
Download project
Funding monitored
€ 246,607.14
of which cohesion funds
€ 246,607.14
Given name | Amount |
---|---|
European Union | 246607.14 |
Payments monitored
€ 246,607.14
of which cohesion funds
€ 246,607.14
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2024 | 246607.14 | 246607.14 | 100 |
State of progress
Completed
Expected start: 13/05/2023
Effective start: 24/07/2023
Expected end: 25/08/2023
Effective end: 11/08/2023
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI VIGONZA
- Beneficiary
- COMUNE DI VIGONZA
- Executor
- COMUNE DI VIGONZA
Programming area
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 246,607.14
- Payments on cohesion funds
- € 246,607.14
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili