CUP: I43C22000500001
Efficientamento energetico di via G. Barbieri
SUMMARY OF THE PROJECT
Efficientamento energetico di via G. Barbieri
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 20,845.77 KWh/a
- Achieved
- 20,845.77 KWh/a
Download project
Funding monitored
€ 57,035.00
of which cohesion funds
€ 57,035.00
Given name | Amount |
---|---|
European Union | 57035.00 |
Payments monitored
€ 57,035.00
of which cohesion funds
€ 57,035.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 57035.00 | 57035.00 | 100 |
State of progress
Completed
Expected start: 02/05/2023
Effective start: 20/07/2023
Expected end: 31/05/2023
Effective end: 25/08/2023
Entities
- Planning body
-
Ministero dell'Ambiente e della Sicurezza Energetica
MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA - Implementing body
- COMUNE DI ABANO TERME
- Beneficiary
- COMUNE DI ABANO TERME
- Executor
- COMUNE DI ABANO TERME
Programming area
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 57,035.00
- Payments on cohesion funds
- € 57,035.00
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili
Other projects in territory
Same theme
Efficientamento energetico di VIA IV NOVEMBRE | € 112,850 |
BRISTOL BUJA S.P.A. - TRIGENERAZIONE | € 74,290 |
Costituzione CER | € 36,990 |