CUP: C14D23000070001
Efficientamento energetico di VIA ROMA
SUMMARY OF THE PROJECT
Efficientamento energetico di VIA ROMA
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 109,948.30 KWh/a
- Achieved
- 97,441.96 KWh/a
Download project
Funding monitored
€ 49,410.00
of which cohesion funds
€ 49,410.00
Given name | Amount |
---|---|
European Union | 49410.00 |
Payments monitored
€ 49,410.00
of which cohesion funds
€ 49,410.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 49410.00 | 49410.00 | 100 |
State of progress
Completed
Expected start: 16/04/2023
Effective start: 07/04/2023
Expected end: 28/07/2023
Effective end: 17/08/2023
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI CASTELLUCCHIO
- Beneficiary
- COMUNE DI CASTELLUCCHIO
- Executor
- COMUNE DI CASTELLUCCHIO
Programming area
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 49,410.00
- Payments on cohesion funds
- € 49,410.00
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili
Other projects in territory
Same theme
Efficientamento energetico di Piazza Pasotti | € 76,860 |
Efficientamento energetico di Piazza Pasotti | € 57,462 |