CUP: I34J23000100001
Efficientamento energetico di via di vittorio
SUMMARY OF THE PROJECT
Efficientamento energetico di via di vittorio
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 21,306.20 KWh/a
- Achieved
- 48,516.31 KWh/a
Download project
Funding monitored
€ 196,909.83
of which cohesion funds
€ 196,909.83
Given name | Amount |
---|---|
European Union | 196909.83 |
Payments monitored
€ 196,909.83
of which cohesion funds
€ 196,909.83
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2024 | 196909.83 | 196909.83 | 100 |
State of progress
Completed
Expected start: 27/04/2023
Effective start: 04/08/2023
Expected end: 30/06/2023
Effective end: 28/08/2023
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI NERVIANO
- Beneficiary
- COMUNE DI NERVIANO
- Executor
- COMUNE DI NERVIANO
Programming area
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 196,909.83
- Payments on cohesion funds
- € 196,909.83
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili
Other projects in territory
Same theme
Efficientamento energetico di Via Torricelli | € 110,000 |