CUP: C74J22000720001
Efficientamento energetico di Via Luranii
SUMMARY OF THE PROJECT
Efficientamento energetico di Via Luranii
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 152,411.43 KWh/a
- Achieved
- 152,411.43 KWh/a
Download project
Funding monitored
€ 63,217.96
of which cohesion funds
€ 63,217.96
Given name | Amount |
---|---|
European Union | 63217.96 |
Payments monitored
€ 63,217.96
of which cohesion funds
€ 63,217.96
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 63217.96 | 63217.96 | 100 |
State of progress
Completed
Expected start: 31/03/2023
Effective start: 20/04/2023
Expected end: 30/06/2023
Effective end: 27/06/2023
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI BRESSO
- Beneficiary
- COMUNE DI BRESSO
- Executor
- COMUNE DI BRESSO
Programming area
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 63,217.96
- Payments on cohesion funds
- € 63,217.96
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili