CUP: H95I22000190001
Efficientamento energetico di Piazza Autonomia
SUMMARY OF THE PROJECT
Efficientamento energetico di Piazza Autonomia
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 30,012.75 KWh/a
- Achieved
- 30,012.75 KWh/a
Download project
Funding monitored
€ 61,699.89
of which cohesion funds
€ 61,699.89
Given name | Amount |
---|---|
European Union | 61699.89 |
Payments monitored
€ 61,065.35
of which cohesion funds
€ 61,065.35
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 61065.35 | 61065.35 | 98 |
State of progress
Completed
Expected start: 26/02/2023
Effective start: 26/02/2023
Expected end: 25/05/2023
Effective end: 26/09/2023
Entities
- Planning body
-
Ministero dell'Ambiente e della Sicurezza Energetica
MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA - Implementing body
- COMUNE DI ROCCAFIORITA
- Beneficiary
- COMUNE DI ROCCAFIORITA
- Executor
- COMUNE DI ROCCAFIORITA
Programming area
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 61,699.89
- Payments on cohesion funds
- € 61,065.35
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili
Other projects in territory
Same theme
Same type of investment
Efficientamento energetico di VIA BELVEDERE | € 144,906 |
Efficientamento energetico di VIA BELVEDERE | € 83,348 |