CUP: C44H22001070001
Efficientamento energetico di Via Benedetto Cairoli
SUMMARY OF THE PROJECT
Efficientamento energetico di Via Benedetto Cairoli
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 97,062.54 KWh/a
- Achieved
- 97,062.54 KWh/a
Download project
Funding monitored
€ 210,042.63
of which cohesion funds
€ 210,042.63
Given name | Amount |
---|---|
European Union | 210042.63 |
Payments monitored
€ 205,358.06
of which cohesion funds
€ 205,358.06
97%
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 205358.06 | 205358.06 | 97 |
State of progress
Completed
Expected start: 01/03/2023
Effective start: 14/07/2023
Expected end: 29/05/2023
Effective end: 22/09/2023
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI PATTI
- Beneficiary
- COMUNE DI PATTI
- Executor
- COMUNE DI PATTI
Programming area
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 210,042.63
- Payments on cohesion funds
- € 205,358.06
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili