CUP: I11I22000350006
EFFICIENTAMENTO ENERGETICO DI PIAZZA LUIGI PIRANDELLO
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO DI PIAZZA LUIGI PIRANDELLO
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 17,525.22 KWh/a
- Achieved
- 17,525.22 KWh/a
Download project
Funding monitored
€ 151,727.74
of which cohesion funds
€ 151,727.74
Given name | Amount |
---|---|
European Union | 151727.74 |
Payments monitored
€ 151,727.74
of which cohesion funds
€ 151,727.74
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 151727.74 | 151727.74 | 100 |
State of progress
Completed
Expected start: 20/02/2023
Effective start: 19/06/2023
Expected end: 30/06/2023
Effective end: 01/09/2023
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI OLIVERI
- Beneficiary
- COMUNE DI OLIVERI
- Executor
- COMUNE DI OLIVERI
Programming area
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 151,727.74
- Payments on cohesion funds
- € 151,727.74
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili
Other projects in territory
Same theme
Same type of investment
EFFICIENTAMENTO ENERGETICO DI VIA BADEN POWELL | € 226,557 |
EFFICIENTAMENTO ENERGETICO DI VIA GASPARE AMODEO | € 89,670 |