CUP: B34D22004230006
Efficientamento energetico di Via F.lli Bandiera
SUMMARY OF THE PROJECT
Efficientamento energetico di Via F.lli Bandiera
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 24,493.70 KWh/a
- Achieved
- 24,493.70 KWh/a
Download project
Funding monitored
€ 86,632.76
of which cohesion funds
€ 86,632.76
Given name | Amount |
---|---|
European Union | 86632.76 |
Payments monitored
€ 66,915.14
of which cohesion funds
€ 66,915.14
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 66915.14 | 66915.14 | 77 |
State of progress
Open
Expected start: 01/03/2023
Effective start: 01/03/2023
Expected end: 30/06/2023
Effective end: 09/05/2023
Entities
- Planning body
-
Ministero dell'Ambiente e della Sicurezza Energetica
MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA - Implementing body
- COMUNE DI SAVIGNANO SUL RUBICONE
- Beneficiary
- COMUNE DI SAVIGNANO SUL RUBICONE
- Executor
- COMUNE DI SAVIGNANO SUL RUBICONE
Programming area
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 86,632.76
- Payments on cohesion funds
- € 66,915.14
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili