CUP: I94D23000210001
Efficientamento energetico di VIA FONTANA
SUMMARY OF THE PROJECT
Efficientamento energetico di VIA FONTANA
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 54,609.40 KWh/a
- Achieved
- 54,609.40 KWh/a
Download project
Funding monitored
€ 199,118.67
of which cohesion funds
€ 199,118.67
Given name | Amount |
---|---|
European Union | 199118.67 |
Payments monitored
€ 188,862.74
of which cohesion funds
€ 188,862.74
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 188862.74 | 188862.74 | 94 |
State of progress
Open
Expected start: 31/05/2023
Effective start: 31/05/2023
Expected end: 30/06/2023
Effective end: 27/09/2023
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI SAN GIORGIO ALBANESE
- Beneficiary
- COMUNE DI SAN GIORGIO ALBANESE
- Executor
- COMUNE DI SAN GIORGIO ALBANESE
Programming area
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 199,118.67
- Payments on cohesion funds
- € 188,862.74
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili
Other projects in territory
Same theme
Same type of investment
Efficientamento energetico di VIA G.MATTEOTTI | € 257,745 |
Efficientamento energetico di VIA ROMA | € 119,688 |
POTENZIAMENTO RACCOLTA RD | € 37,207 |
Un Computer per amico | € 17,983 |
SCIENZE IN LABORATORIO | € 15,000 |