CUP: I94D23000130001
Efficientamento energetico di VIA ROMA
SUMMARY OF THE PROJECT
Efficientamento energetico di VIA ROMA
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 85,515.26 KWh/a
- Achieved
- 85,515.26 KWh/a
Download project
Funding monitored
€ 119,688.29
of which cohesion funds
€ 119,688.29
Given name | Amount |
---|---|
European Union | 119688.29 |
Payments monitored
€ 107,996.51
of which cohesion funds
€ 107,996.51
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 107996.51 | 107996.51 | 90 |
State of progress
Open
Expected start: 30/05/2023
Effective start: 30/05/2023
Expected end: 30/06/2023
Effective end: 27/09/2023
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI SAN GIORGIO ALBANESE
- Beneficiary
- COMUNE DI SAN GIORGIO ALBANESE
- Executor
- COMUNE DI SAN GIORGIO ALBANESE
Programming area
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 119,688.29
- Payments on cohesion funds
- € 107,996.51
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili
Other projects in territory
Same theme
Same type of investment
Efficientamento energetico di VIA G.MATTEOTTI | € 257,745 |
Efficientamento energetico di VIA FONTANA | € 199,119 |
POTENZIAMENTO RACCOLTA RD | € 37,207 |
Un Computer per amico | € 17,983 |
SCIENZE IN LABORATORIO | € 15,000 |