CUP: B24H23000020001
EFFICIENTAMENTO ENERGETICO DI VIALE DELLA REPUBBLICA
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO DI VIALE DELLA REPUBBLICA
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 44,077.74 KWh/a
- Achieved
- 0 KWh/a
Funding monitored
€ 248,941.00
of which cohesion funds
€ 248,941.00
Given name | Amount |
---|---|
European Union | 248941.00 |
Payments monitored
€ 248,941.00
of which cohesion funds
€ 248,941.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 248941.00 | 248941.00 | 100 |
State of progress
Completed
Expected start: 30/03/2023
Effective start: 30/03/2023
Expected end: 30/06/2023
Effective end: 26/09/2023
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI SAN LORENZO BELLIZZI
- Beneficiary
- COMUNE DI SAN LORENZO BELLIZZI
- Executor
- COMUNE DI SAN LORENZO BELLIZZI
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili