CUP: G89I22001320001
EFFICIENTAMENTO ENERGETICO DI VIA FIRENZE
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO DI VIA FIRENZE
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 17,675.20 KWh/a
- Achieved
- 18,552.69 KWh/a
Funding monitored
€ 253,394.00
of which cohesion funds
€ 253,394.00
Given name | Amount |
---|---|
European Union | 253394.00 |
Payments monitored
€ 253,394.00
of which cohesion funds
€ 253,394.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 253394.00 | 253394.00 | 100 |
State of progress
Completed
Expected start: 01/03/2023
Effective start: 15/02/2023
Expected end: 15/06/2023
Effective end: 12/06/2023
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI MIRABELLO SANNITICO
- Beneficiary
- COMUNE DI MIRABELLO SANNITICO
- Executor
- COMUNE DI MIRABELLO SANNITICO
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili