CUP: D44H23000060001
EFFICIENTAMENTO ENERGETICO DI VIA TORINO
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO DI VIA TORINO
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 14,349.90 KWh/a
- Achieved
- 42,083.12 KWh/a
Download project
Funding monitored
€ 85,473.77
of which cohesion funds
€ 85,473.77
Given name | Amount |
---|---|
European Union | 85473.77 |
Payments monitored
€ 66,911.16
of which cohesion funds
€ 66,911.16
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 66911.16 | 66911.16 | 78 |
State of progress
Open
Expected start: 29/04/2023
Effective start: 11/07/2023
Expected end: 28/05/2023
Effective end: 09/08/2023
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI OVADA
- Beneficiary
- COMUNE DI OVADA
- Executor
- COMUNE DI OVADA
Programming area
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 85,473.77
- Payments on cohesion funds
- € 66,911.16
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili