CUP: D63I23000030001
EFFICIENTAMENTO ENERGETICO DI PIAZZA MATTEOTTI
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO DI PIAZZA MATTEOTTI
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 50,022.29 KWh/a
- Achieved
- 50,022.29 KWh/a
Download project
Funding monitored
€ 166,260.92
of which cohesion funds
€ 166,260.92
Given name | Amount |
---|---|
European Union | 166260.92 |
Payments monitored
€ 166,260.28
of which cohesion funds
€ 166,260.28
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Completed
Expected start: 01/04/2023
Effective start: 23/10/2023
Expected end: 30/06/2023
Effective end: 17/11/2023
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI STREVI
- Beneficiary
- COMUNE DI STREVI
- Executor
- COMUNE DI STREVI
Programming area
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 166,260.92
- Payments on cohesion funds
- € 166,260.28
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili